Voorhees Township Board of EducationApr 18, 2023Documents
2023-2024 LRFP Working Copy - Board Approval 2023.04.18 (1)
Summary
This is Voorhees Township's 2023-2028 Long Range Facilities Plan, a list of building repairs and upgrades planned for each school over the next five years. It covers things like new roofs, HVAC systems, windows, security cameras, solar panels, and a major preschool expansion, with cost estimates for each item. The total projected cost across all schools and the administration building is about $59.9 million, with roughly $35.9 million (60%) potentially eligible for state funding support.
Generated by Claude Sonnet 5
Raw text
The text of the document, as Citizen AI read it from the file. The file itself is the official copy.
Page 1
Board Approval 2023.04.18
Voorhees Township Board of Education
2023-2028 LRFP
Estimated
Project Start
Fiscal Year Units Price Total
Hamilton School
Replace Interior Doors 2021-2025 35 $ 2,000 $ 70,000
Replace Windows (energy saving insulated) 2021-2025 40 $ 5,000 $ 200,000
Replace HVAC units 2021-2025 30 $ 18,000 $ 540,000
Installation of additional security systems 2021-2025 2 $ 100,000 $ 200,000
Installation of fencing 2025 1 $ 300,000 $ 300,000
Refurbish Student & Faculty Bathrooms 2021-2025 8 $ 15,000 $ 120,000
Replace carpeting 2021-2025 20 $ 12,000 $ 240,000
Replace HVAC (computerized control system) 2023 25 $ 3,000 $ 75,000
Install FOB system 2024 1 $ 50,000 $ 50,000
Fire alarm system replacement 2024-2025 1 $ 470,000.00 $ 470,000
Solar 2025 1 $ 1,500,000 $ 1,500,000
Replace metal roof 2025 1 $ 1,750,000 $ 1,750,000
Total $ 5,515,000
Kresson School
Replace metal roof 2025 1 $ 5,200,000 $ 5,200,000
Replace Interior Doors 2021-2025 35 $ 2,000 $ 70,000
Replace HVAC units 2021-2025 25 $ 18,000 $ 450,000
Installation of additional security systems 2021-2025 2 $ 100,000 $ 200,000
Replace Windows (energy saving insulated) 2021-2025 30 $ 5,000 $ 150,000
Refurbish Student & Faculty Bathrooms 2021-2025 8 $ 15,000 $ 120,000
Expansion to Maintenance Garage 2024 1 $ 150,000 $ 150,000
Replace carpeting 2021-2025 20 $ 12,000 $ 240,000
Replace HVAC (computerized control system) 2023 25 $ 3,000 $ 75,000
Install FOB system 2024 1 $ 50,000 $ 50,000
Fire alarm system replacement 2024-2025 1 $ 455,000.00 $ 455,000
Solar 2025 1 $ 1,500,000 $ 1,500,000
Media Center Renovations 2024 1 $ 250,000 $ 250,000
Total $ 8,910,000
Osage School
Replace Interior Doors 2021-2025 40 $ 2,000 $ 80,000
Replace Windows (energy saving insulated) 2021-2025 10 $ 5,000 $ 50,000
Installation of additonal security systems 2021-2025 2 $ 100,000 $ 200,000
Installation of fencing 2025 1 $ 150,000 $ 150,000
Replace HVAC units 2021-2025 20 $ 18,000 $ 360,000
Refurbish Student & Faculty Bathrooms 2021-2025 8 $ 15,000 $ 120,000
Replace carpeting 2019-2024 20 $ 12,000 $ 240,000
Replace metal roof 2025 1 $ 1,750,000 $ 1,750,000
Replace HVAC (computerized control system) 2023 25 $ 3,000 $ 75,000
Fire alarm system replacement 2024-2025 1 $ 582,000.00 $ 582,000
Boiler replacement 2024-2025 1 $ 1,440,000.00 $ 1,440,000
Solar 2025 1 $ 1,500,000 $ 1,500,000
Install FOB system 2024 1 $ 50,000 $ 50,000
Upgrade lighting to LED 2024 1 $ 250,000 $ 250,000
Playground Upgrade & Site Preparation 2023-2024 1 $ 582,000 $ 250,000
Total $ 7,097,000
Signal Hill
Replace Interior Doors 2021-2025 20 $ 2,000 $ 40,000
Replace HVAC units 2021-2025 45 $ 18,000 $ 810,000
Replace Windows (energy saving insulated) 2021-2025 20 $ 5,000 $ 100,000
Page 2
Board Approval 2023.04.18
Refurbish Student & Faculty Bathrooms 2021-2025 8 $ 15,000 $ 120,000
Installation of additional security systems 2021-2025 2 $ 100,000 $ 200,000
Reasphalt parking lot and driveway 2023 1 $ 300,000 $ 300,000
Playground equipment 2023 1 $ 300,000 $ 300,000
Replace carpeting 2019-2024 20 $ 8,000 $ 160,000
Fire alarm system replacement 2024-2025 1 $ 608,000.00 $ 608,000
Boiler replacement 2024-2025 1 $ 1,497,000.00 $ 1,497,000
Solar 2025 1 $ 1,500,000 $ 1,500,000
Install FOB system 2024 1 $ 50,000 $ 50,000
Replace HVAC (computerized control system) 2024 45 $ 3,000 $ 135,000
Total $ 5,820,000
Middle School
Replace Interior Doors 2021-2025 50 $ 2,000 $ 100,000
Installation of additional security systems 2021-2025 3 $ 100,000 $ 300,000
Replace Windows (energy saving insulated) 2021-2025 30 $ 5,000 $ 150,000
Refurbish Student & Faculty Bathrooms 2021-2025 10 $ 15,000 $ 150,000
Replace HVAC units (School) 2021-2024 76 $ 20,000 $ 1,520,000
Replace glass blocks (Theater) 2023-2024 1 $ 50,000 $ 50,000
Upgrade House Lighting to LED (Theater) 2022-2024 1 $ 150,000 $ 150,000
Replace carpeting 2019-2024 40 $ 8,000 $ 320,000
Replace fencing and ballards 2021-2025 1 $ 350,000 $ 350,000
Solar 2025 1 $ 2,500,000 $ 2,500,000
Install FOB system 2024 1 $ 75,000 $ 75,000
HVAC Equipment 2024-2025 1 $ 1,216,000 $ 1,216,000
Replace metal roof 2025 1 $ 2,500,000 $ 2,500,000
Replace HVAC (computerized control system) 2021-2025 5 wings $ 20,000 $ 100,000
Glass block replacement - Auditorium Lobby 2024-2025 1 $ 380,000 $ 380,000
Artificial Turf Athletic Fields 2025 1 $ 3,500,000 $ 3,500,000
Total $ 13,361,000
District-wide
Preschool Expansion - Additional Classrooms - Phase I 2023-2024 1 $ 11,000,000 $ 11,000,000
Preschool Expansion - Additional Classrooms - Phase 2 2024-2025 1 $ 7,000,000 $ 7,000,000
$ 18,000,000
Adm Building
Convert to Municipal Water and Sewer 2025 1 $ 250,000 $ 250,000
Reasphalt parking lot 2025 1 $ 150,000 $ 150,000
Security camera installation 2023 5 $ 8,000 $ 40,000
Install FOB system 2024 1 $ 25,000 $ 25,000
Reconfigure roof drainage 2023 1 $ 650,000 $ 650,000
Refurbish Bathrooms 2023 4 $ 10,000 $ 40,000
Total $ 1,155,000
Grand Total $ 59,858,000
60% ($ 35,914,800)