Voorhees Township CommitteeMay 27, 2025Documents
Resolution 182-25: Accepting a Contract and Performance Bond for Mac-rose Contractors, Inc. for the Lawnside Force Main Project
Passed3-0See the vote
Summary
Accepts the signed contract and a $146,050 performance bond from Mac-Rose Contractors, Inc. for the Lawnside sewer force main replacement project, after township engineers and the solicitor reviewed and approved the paperwork.
Generated by Claude Sonnet 5
Raw text
As it reads in the agenda packet. View it in the packet
RESOLUTION NO. 182-25
ACCEPTING A CONTRACT AND PERFORMANCE BOND FOR MAC-ROSE CONTRACTORS, INC. FOR THE LAWNSIDE FORCE MAIN PROJECT
WHEREAS, on May 12, 2025, Voorhees Township Committee awarded the Lawnside Force Main Project to Mac-Rose Contractors, Inc; and
WHEREAS, Churchill Engineers and Christopher Long, Township Solicitor have reviewed the contract, performance and payment bond and advise that they are approved as to form and sufficiency ; and
WHEREAS, Voorhees Township is in receipt of Performance Bond #BU101888 in the amount of $146,050.00 from First Indemnity of America Insurance Company dated May 15, 2025.
NOW, THEREFORE, BE IT RESOLVED, by the Mayor and Township Committee that the above-mentioned contract, performance and payment bond be approved and accepted.
DATED: MAY 27, 2025 MOTION:
AYES: SECONDED:
NAYS: APPROVED BY: ________________________________
Michael Mignogna, Mayor
I, Dee Ober, Municipal Clerk of the Township of Voorhees, hereby certify the foregoing to be a true and correct copy of a resolution adopted by the Mayor and Township Committee of the Township of Voorhees at their meeting of May 27, 2025, held in the Municipal Building, 2400 Voorhees Town Center, Voorhees, NJ 08043.
____________________________
Dee Ober, RMC
Township Clerk