Voorhees Township CommitteeJan 20, 2026Documents

Resolution 55-26: Approving Change Order #1 for the Echelon Center Pedestrian Improvements Project to Charles Marandino, LLC ($105,765.97 Increase)

Pages 10 to 11 of the agenda packetFrom the Voorhees Township Town Committee Meeting January 20, 2026, Resolutions.

Passed4-0See the vote

View it in the packet

Summary

Increases the contract with Charles Marandino, LLC for the Echelon Center Pedestrian Improvements Project by $105,765.97 (from $1,140,367.00 to $1,246,132.97) to account for actual quantities of work differing from the original contract estimate.
Generated by Claude Sonnet 5

Raw text

As it reads in the agenda packet. View it in the packet

RESOLUTION NO. 55-26 APPROVING CHANGE ORDER #1 FOR THE ECHELON CENTER PEDESTRIAN IMPROVEMENTS PROJECT TO CHARLES MARANDINO, LLC ($105,765.97 INCREASE) WHEREAS, a contract in the amount of $1,140,367.00 was awarded to Charles Marandino, LLC on November 11, 2025 by Resolution #271-24, for the Echelon Center Pedestrian Improvements Project; and WHEREAS, an amendment to the original contract is necessary due to the adjustment of as-built quantities versus contract quantities, resulting in a net increase in the amount of $105,765.97, and an adjusted contract in the amount of $1,246,132.97. NOW, THEREFORE, BE IT RESOLVED by the Mayor and Township Committee that Change Order #1 in the net amount of $105,765.97 (increase), which amends the original contract with Charles Marandino, LLC for the Echelon Center Pedestrian Improvements Project, is hereby approved. DATED: JANUARY 20, 2026 MOTION: AYES: SECONDED: NAYS: APPROVED BY: _____________________________ Michael Mignogna, Mayor I, Dee Ober, Municipal Clerk of the Township of Voorhees hereby certify the foregoing to be a true and correct copy of a resolution adopted by the Mayor and Township Committee of the Township of Voorhees at their meeting of January 20, 2026 held in the Municipal Building, 2400 Voorhees Town Center, Voorhees, NJ 08043. ____________________________ Dee Ober, RMC Township Clerk